Timeline for Milestones (2005)
March
Beginning - Experiment selection, NOVESPACE is contacting and asking for an update of the Experimental Form. Medical Examination - OK
23 - Experimental form to be updated and sent back to NOVESPACE. - OK
29 - NOVESPACE will send 2 forms to be filled in and sent back to them: A model for presenting the experiment to journalists and other students and a Liability form.
29 - 31 - SPFC 2005 Workshop
April
13 - NOVESPACE will visit the experiment in order to validate the experiment design and building. The experiment should be complete as much as possible (every piece of hardware should be shown to NOVESPACE), although the experimental rack does not need to be built.
May
23 - All technical design has to be frozen. No change on the experiment should occur except the ones requested by CEV.
June
3 - List of participants and medical documents should have been sent to NOVESPACE
14 - Safety Review meeting between ESA, NOVESPACE and CEV. NOVESPACE is presenting experiments. During the meeting, some changes could be requested and some comments could arise. Change requests and comments will be provided to experimenters.
15 - Experiment description for journalists and students should be sent back to NOVESPACE.
23 - Filled liability forms to be sent to NOVESPACE.
July
12 - 20 - Flight Campaign Group 1
19 - 27 - Flight Campaign Group 2

 